You auctions of energy generation and transmission carried out by the Ministry of Mines and Energy this Friday (3) ended with the movement of just over R$ 490 million, with contracts that will start from January 2022.
The first auction, “A-1”, had the contracting of 66 average megawatts (MW), equivalent to 1,156 gigawwatts-hour (GWh). The average price was BRL 209.25 per MWh, 12.81% lower than the initial bid determined by the National Electric Energy Agency (Aneel), of BRL 240 per MWh.
The auction involves companies Cemar and Celpa, from Equatorial Energia, as buyers, with the former responsible for 75% of the energy purchased, and the latter for 25%. The sellers were the companies Alupar, Copel and Safira.
The total movement was R$ 241.96 million in contracts. The “A-1” auction did not specify the type of energy generation, but it is anticipated that the costs with hydrological risks will be assumed by the sellers.
The “A-2” auction accepted contracts by availability for thermoelectric power plants with generation via natural gas, process gas, national mineral coal and biomass, or by quantity, regardless of the generating source. The starting price was R$200.
Cemar and Celpa were also buyers, along with CPFL Jaguari. The energy sellers were Eletronorte, Kroma, Maxima Energia and Vivaz Energia. The total movement was R$ 249.08 million in contracts.
The contracts start on January 1, 2022 and end on December 31, 2023.
Energy Weeks
The auction this Friday (3) is part of a series of auctions that will take place until December 21, called “Energy Weeks” by the Ministry of Mines and Energy. The expectation is to collect R$ 206.9 billion in private investments from the concessions, generating 160 thousand direct and indirect jobs.
The next auction will take place on December 17, when the surplus from the onerous transfer of oil in the pre-salt will be offered in the Sépia and Atapu fields. The government is expected to raise R$ 120 billion, generating 160,000 direct and indirect jobs.
On the same day, a new energy transmission auction will take place, which foresees the construction of 902 kilometers of transmission lines. The planned investment will be of R$ 2.9 billion, with around 6,000 jobs created. The project involves the states of Amapá, Bahia, Minas Gerais, Paraná and São Paulo.
On the 21st, there will be an auction for contracting power and electricity from new and existing thermoelectric plants. The start of the supply of this energy is scheduled for 2026 and 2027, with 15-year contracts.
*With information from Reuters
Reference: CNN Brasil

I am Sophia william, author of World Stock Market. I have a degree in journalism from the University of Missouri and I have worked as a reporter for several news websites. I have a passion for writing and informing people about the latest news and events happening in the world. I strive to be accurate and unbiased in my reporting, and I hope to provide readers with valuable information that they can use to make informed decisions.